2021: 01–01 — Extending Syslinks

<Extending Syslinks>

Project Proposal

<version>
<author> - <admin1@syscoin.network>

1. General Project Information

Project Name: <Extending Syslinks>
Project Manager: <MooBaa>
Link: <link to your proposal on syshub>
Vote: <console command to vote for your proposal>

  • Open Syscoin-Qt
  • Select Tools > Console from the top menu
  • Copy and paste the following command onto one line, and hit enter:
    gobject vote-many
    f4e517aa1039561c4338ce261bbfa463167434a87c212b38006fe217342a55e1 funding yes

2. Description

Continually updating the popular and widely used Syslinks link collection at https://syscoin.network/syslinks with any links that become available and retweeting those additional links through the Twitter account @Sysnetsite, Syslinks is marketed as “THE complete and up-to-date link collection for the Syscoin Platform”,

Syslinks is continuously evolving. With the addition of marketing teams for Latin and South America and the status of Marketing Team Asia being elevated,two respective categories were created on Syslinks so that users can easily find post and articles of those respective marketing teams.

Posts on relevant news on https://publish0x.com were created in support and increase awareness of the Syslinks resource and of Syscoin. The blog Sysnetsite | Publish0x (Sysnetsite) on publish0x has more than 350 followers and the posts so far have generated more than 75k views on this crypto friendly website in total! following the link will provide a complete list of all articles posted so far. Follow this link for the latest post in January 2021:
Syscoin to be in the Limelight as Govt Agency OKs Stablecoins

3. Status RAG (Red, Amber, Green)

Status Time Budget Risks
Complete:
Green:
Amber:
Red:
**RAG Status Guideline**
Status Time Budget Risks
Green: Key milestones are met and critical path and delivery end date are not affected. Cost variance is < 10% of lifetime cost. No risk is reported Amber or Red.
Amber: One or several key milestones cannot be met but critical path and delivery end date are not affected. Cost variance is 10%-20% of lifetime cost. At least one risk is reported as Amber and none is reported as Red.
Red: One or several key milestones cannot be met. Critical path and delivery end date are affected. Cost variance is >= 20% of lifetime cost. At least one risk is reported as Red.

4. Overall Status

<continuous>

5. Progress and Achievements Since Last Reporting Period

<continous>

6. Time

<daily check and website updates of any emerging links etc. >

7. Budget

`Sys 4567

8. Risks

<risk planning>